Production orders created in ECC is respecting the holidays as per the factory calendar, but while updating the production order to APO it’s NOT considering the holidays.
And the Order quantity also gets changed/split in APO, could someone help me to understand the calculation please.
I have verified the resource masterdata and buccket capcity and ran cons check & saved Resouce live cache. And checked Time stream as well, everything looks fine.
Please refer the below screen shot for more details and let us know the best way to overcome this situation.
Thanks for your help in advance.
MD04:
APO:
Regards,
Ravindran PG