Hi Everyone,
Thanks for giving me an opportunity to share my question over here.
My concern is related to meter read order creation for a particular scenario. Say, for some xyz account, we have periodic Scheduled Meter Read Date on 30.09.2015. The read has been successfully updated ("01" Meter Read)as well satisfying the particular order.
Now if the account moves out on the same date i.e. 30.09.2015, then business movers are amending Move-out read ("03" read) on the same date.
Now both "01" and "03" are billable read. Though logically the read with lesser priority should get suppressed but how do system should behave in such cases to avoid any conflict causing billing error ?
Many Thanks,
Krishanu.