Dear Friends,
In cor6n my client wants to change the more then 6 activity .
if I assigned in c202 2 work center with 5+ 6 activity system throw error in cor6n‘phase/
Operation in process order does not exist.
Please find the attached screen shot.
Please suggest me how to solve the issue.
Regards.
Sabhapathy R