No Measurement doc available before &date &time for counter # Plan #- although Measurement docs exist in system.

$
0
0

Hello experts,

I am trying to schedule a multiple counter maintenance plan. I have set up the cycle/unit for the measuring points as 20 EA and 30 EA. I am creating measurement documents manually through transaction codes IK11, such that counter value for first meas. pt. is 40 while the second one is only at 20.

Now, when I am trying to schedule the plan, I am getting the following error. I have tried both IP10 and IP30.

When I tried to start the cycle, it asked me for the time and date and I went ahead with what was proposed in the pop-up box. That was 06/08/2016  09:18:15.

error.jpg

I have tried to start the cycle by giving a time before the creation of measurement documents as well as a time after their creation. Either way, I am stuck. The odd thing is that this problem was not happening earlier. It started only a day back and in between I have not changed any configuration at all.

Please refer to the following screenshots for the plan details. I have created the plan using transaction code IP01.

plan1.jpg

plan2.jpg

Here are the measuring docs for the meas. pts., along with the measurement times. You can see the current system time also.

IK17.jpg

I have faced similar kind of issue for both multiple counter plan and plan based on both time and performance basis.

Wherever measurement docs are involved, there seems to be a problem.

 

Please help as this needs to be resolved quickly.