Hi,
While iam creating process order using T-code COR1, iam entered total qty 150 L ,here scheduling type : Backwards
and i entered the finish date 12.07.2012. can also please look into the snapshot.
then iam getting below error message :
Date 12.07.2016 is earlier than the validity period of the factory calendar
Message no. CO033
Procedure
Enter a date which lies withing the validity period of the factory calendar.
but I have not maintained the factory calendar in the resource(capacity).
Can you please resolve the issue.
Regards,
Sree.