In order to anticipate materials for a prolonged machine maintenance, we've created a calender to apply to that specific work center with the days of maintenance closed. Changes were also made to Schedulling in CR02.
However, we are still getting requirements planned in the period that should be closed.
This doesn't happen when we do a general plant shutdown.
Can anyone assist me in this issue?