Hi,
When I choose current date scheduling type during production order creation, after scheduling it is adjusted to a future date i.e.
If basic start date: 09/09/2015
then after scheduling it is adjusted to 12/09/2015.
In the first operation following interoperation times are maintained
Standard queue time: 2.5 day (maintained in the operation)
Standard queue time: 2.5 day (maintained in the work center scheduling view)
Note that as per factory calendar all are work days
Can any one guide in this systems behaviour.
Thanks in advance
BR
Raghava